Amendment type nr. | Amendment type | - Automatically selected by the system after the updates have been done, or
- to be manually selected by the Project Officer or the Beneficiary
- On-demand: requested by the Project Officer from the Service Desk
| Relevant SyGMa tab*
* the changes are applied immediately, but you will still have to set the amendment type (automatically/manually) afterwards to deal with the consequences of the change | How to apply the changes | Relevant GA articles | |
---|
Amendment types that can be activated only by the Commission/Agency The Commission/Agency must be contacted before requesting these amendment types ** Amendment types also available after the end date of the project (but NOT after the final payment) or after the termination date |
---|
AT1
| Addition of a new beneficiary *Consortium Requested amendment
If a beneficiary is terminated due to non-accession or other reason and it re-enters in the project via an amendment, then it should (re-)sign the Accession Form and the Declaration of Honour. | Automatic | Beneficiaries | Click on Add new beneficiary to add a new beneficiary
Search for the PIC you would like to add
Select the line of the PIC
Add the short name and select the type of start date
If the beneficiary has been terminated due to non-accession or other reason and it re-enters in the project via an amendment, then the following message is displayed: The new beneficiary is now flagged as new. Click on the replace, delete or edit icon to update the new beneficiary.
To change the participation (e.g. requesting zero funding) of the newly-added beneficiary/affiliated entity, follow the instructions for editing the beneficiary's Financial Information during grant preparation that you can find here. Adding a new beneficiary will automatically set the "Addition of a new Beneficiary" and "Changes to Annex 1" amendment types:
When adding a new Beneficiary that is an International Organisation, you have the option to change the applicable law regime and the dispute settlement forum. See AT16 and AT17 for more information.
| Data sheet - Section 2 - List of Participants (Article 7) |
|
AT2 | Addition of an Affiliated Entity *Consortium Requested amendment
| Automatic | Beneficiaries - Affiliated Entities | Click on Add new Affiliated Entity to add a new Affiliated Entity
Search for the PIC you would like to add
Select the line of the PIC
Add the short name and select the type of start date
The new Affiliated Entity is now flagged as new
Click on the replace, delete or edit icon to update the new Affiliated Entity
Adding a new Affiliated Entity will automatically set the "Addition of an affiliated entity" amendment type:
| Data sheet - Section 2 - List of Participants (Article 8)
| If Affiliated Entities is applicable |
AT3 | Addition of an Associated Partner *Consortium Requested amendment | Automatic | Associated Partners | Click on Add New Associated Partner to add a new Associated Partner
Search for the PIC you would like to add
Select the line of the PIC
Add the short name and select the type of start date
The new Associated Partner is now flagged as new
Click on the replace, delete or edit icon to update the new Associated Partner
Adding a new Associated Partner will automatically set the "Addition of an associated partner" amendment type:
To link an Associated Partner to a Beneficiary, select the relevant Associated Partner and then select the Beneficiary from the Associated with drop down.
After this, you can click the Undo button to revert back to the previous entry.
If the Associated Partner is linked to a Beneficiary that is no longer active (i.e. terminated or not acceded), you must manually update the Associated Partner's "Associated with" data. Either by associating with another beneficiary or removing the association.
| Data sheet - Section 2 - List of Participants (Article 9.1) | If Associated Partners is applicable |
AT4
| Beneficiary Termination *Consortium Requested amendment
| Automatic | Beneficiaries | Please click here for more information. | Data sheet - Section 2 - List of Participants (The entry will be in strikeout format) | |
AT5
| Beneficiary termination (non-accession to the GA) *Commission Initiated amendment (or) *Consortium Requested amendment | Automatic | Beneficiaries | Click on the cross icon to remove the beneficiary that has not signed the accession form (not acceded).
Confirm the removal of the beneficiary and its Affiliated Entities.
The beneficiary is now flagged as not acceded. If the Beneficiary has Affiliated Entities linked to it, they will also be terminated and flagged as not acceded.
If the Beneficiary has Associated Partners linked to it, they will also be terminated and flagged as not acceded.
Click on the undo button to undo the removal. This will undo the removal of the Beneficiary and all linked Affiliated Entities and Associated Partners.
| Data sheet - Section 2 - List of Participants (Article 32.3.1(a)) |
|
AT6
| Removal of an Affiliated Entity *Commission Initiated amendment (or) *Consortium Requested amendment
| Automatic | Beneficiaries - Affiliated Entities | Please click here for more information. | Data sheet - Section 2 - List of Participants (The entry will be in strikeout format) | If Affiliated Entities is applicable
|
AT7
| Removal of an Associated Partner *Commission Initiated amendment (or) *Consortium Requested amendment
| Automatic | Associated Partners | Please click here for more information. | Data sheet - Section 2 - List of Participants (The entry will be in strikeout format) | If Associated Partners is applicable
|
AT11** | Change of the coordinator *Consortium Requested amendment
For a change of the coordinator, contact the Commission/Agency before preparing your amendment (mandatory) This amendment type is also available after the end date of the project (but NOT after the final payment) or after the termination date | Automatic | Beneficiaries | Click Change coordinator to change the coordinator Nominate the new coordinator, select the date they will be effective from and indicate whether you want to terminate the old coordinator Enter details of the new primary coordinator contact and click save.
Changing the coordinator will automatically set the "Change of coordinator" and "Change of annex 1" amendment types: In the case when a new coordinator is joining the consortium (i.e. (s)he is not an active beneficiary), the project legal signatory (PLSIGN) has to sign also a Declaration of Honour (DoH) and the Accession Form.
| Data sheet - Section 2 - Coordinator |
|
AT12** | Change of the bank account for payments *Consortium Requested amendment
This amendment type is also available after the end date of the project (but NOT after the final payment) or after the termination date This amendment type can be flagged as Error Amendment by the EU Officer | Automatic | Coordinator bank account - except JRC (bank account has to be validated in ABAC, otherwise SyGMa won't show it) | Click Select bank account to change bank account
Enter the last four IBAN digits of the account
Click on the bank account number appearing and click select
The new bank account is now displayed. Click Save.
You can revert back to the original bank account details by clicking the Undo button.
Changing the bank account will automatically set the "Change of the bank account for payments" amendment type:
| Data sheet - Section 4.2 Periodic reporting and payments |
|
AT15 | Change of the participant short name *Commission Initiated amendment (or) *Consortium Requested amendment
This amendment type can be flagged as Error Amendment by the EU Officer
| Automatic | Partner Summary | Modify the short name of the Beneficiary, Affiliated Entity and/or Associated Partner and save your changes
You can revert back to the previous short name by clicking the Undo button.
Changing the short name for a Beneficiary, Affiliated Entity or Associated Partner, will automatically set the "change of the participant short name" type:
| Data sheet - Section 2 - List of Participants |
|
AT16 | Change of applicable law regime *Consortium Requested amendment
This amendment type is not applicable for FPAs. This amendment type can be flagged as Error Amendment by the EU Officer | Automatic | Beneficiaries - Partner Summary | When adding a new Beneficiary that is an International Organisation, you have the option to change the applicable law regime. In the Partner summary screen, click the change button
Change the applicable law and click OK
Click save
In the Amendment Information screen, the amendment type "Change of applicable law regime" will be automatically set.
| Data sheet - 5. Consequences of non-compliance, applicable law & dispute settlement forum | If GA options GAO77a & GAO77b are applicable |
AT17 | Change of dispute settlement forum *Consortium Requested amendment
This amendment type is not applicable for FPAs. This amendment type can be flagged as Error Amendment by the EU Officer
| Automatic | Beneficiaries - Partner Summary | When adding a new Beneficiary that is an International Organisation, you have the option to change the dispute settlement forum. In the Partner summary screen, click the change button
Change the dispute settlement and click OK
Click save
In the Amendment Information screen, the amendment type "Change of dispute settlement forum" will be automatically set.
| Datasheet - 5. Consequences of non-compliance, applicable law & dispute settlement forum | If GA options GAO78 is applicable |
AT18 | Change of associated partner link *Consortium Requested amendment
This amendment type can be flagged as Error Amendment by the EU Officer | Automatic | Associated Partners | From the Associated Partners screen click on the Associated Partner for which you wish to check/modify the association link.
Click on the pencil icon to edit/change the associated partner link. Choose the beneficiary to be associated with and set the date of the new association. This can be: - a fixed date,
- the accession date of the new beneficiary (if the association is with a new beneficiary) or
- the termination date of the old beneficiary (if in the past you were associated with a beneficiary that was terminated).
In the Amendment Information screen, the amendment type "AT18 Change of associated partner link" will be automatically set.
To undo the association, click the Undo button and Confirm.
Click History, to view the history of Beneficiary associations for an Associated Partner:
| Data sheet - 9.1 Associated partners | If Associated partners is applicable |
AT21** | Change of Annex 1 (description of the action) *Commission Initiated amendment (or) *Consortium Requested amendment
This amendment type is also available after the end date of the project (but NOT after the final payment) or after the termination date
This amendment type can be flagged as Error Amendment by the EU Officer
| - Automatically set as a change resulting from an other type (see column impact on other amendment types)
- Manually set by the PO in all other cases
| Amendment information | The following amendment types will automatically trigger the setting of the "Change of annex 1" amendment type: - AT1: Addition of new beneficiary
- AT2: Addition of an affiliated entity
- AT3: Addition of an associated partner
- AT4: Beneficiary termination
- AT5: Beneficiary termination (non-accession to the GA)
- AT6: Removal of an affiliated entity
- AT7: Removal of an associated partner
- AT11: Change of the coordinator
- AT15: Change of participant short name
- AT50: Change concerning listed equipment
- If a new Annex 1 part B (case 1.a) is added
The following changes of project data will automatically trigger the setting of the "Change of annex 1" type: - Any change to Work Packages
- Any change to Deliverable
- Any change to Milestones
- Any change to Critical Risks
- Any change to Project Reviews
- Any change to recruitmentsRecruitments*
- Any change to secondmentsSecondments
- Any change to Infrastructures
- Any change to JU Contributions
- Any change to Project Abstract project abstract
- Any change to staff exchangesStaff Exchanges
- Any change to Principal Investigator data
- Any change to Projects of Common Interest
*For MSCA-DN projects: The "family allowance" may be amended but only by the EU, via a Commission Initiated amendment, at the end of the project, in the rare case when the maximum grant amount is exceeded. If necessary, edit the date for when the changes will start to apply: - Click on the pencil icon
Show If |
---|
group | it-administrators, it-view-rightsSYGMA-52373 - SyGMa 23.2, add this info to the list above: - Any change to JU Contributions
|
---|
| Annex 1 |
|
AT22 | Change of the project name *Commission Initiated amendment (or) *Consortium Requested amendment
This amendment type can be flagged as Error Amendment by the EU Officer | Automatic | General Information | Change the project title and click save.
Changing the project title will automatically set the "Change of the project title" amendment type:
| Data sheet - 1. General data |
|
AT23 | Change of the project acronym *Commission Initiated amendment (or) *Consortium Requested amendment
This amendment type can be flagged as Error Amendment by the EU Officer | Automatic | General Information | Change the project acronym and click save.
Changing the project acronym will automatically set the " Change of the project acronym " amendment type:
| Data sheet - 1. General data |
|
AT24 | Change of the project starting date *Commission Initiated amendment (or) *Consortium Requested amendment
This amendment type can be flagged as Error Amendment by the EU Officer Please note that changing the project start date is NOT allowed and it cannot be edited (it remains read-only) in certain situations like, for e.g. when a REPA (periodic reporting) is ongoing or completed. | Automatic | General information | Edit the project starting date and click Save.
After this, you can still edit the date by clicking the Undo button.
When finished, click Save. Changing the project starting date will automatically set the "Change of the project starting date" amendment type:
| Data sheet - 1. General data | |
AT25
| Change of the project duration *Commission Initiated amendment (or) *Consortium Requested amendment
This amendment type can be flagged as Error Amendment by the EU Officer Please note that changing the project duration is NOT allowed and it cannot be edited (it remains read-only) in certain situations like, for e.g. when the last REPA or FINA is ongoing or completed.
| Automatic | General information | Edit the project duration and Save .
After this, you can still edit the date by clicking the Undo button. When finished, click Save. Changing the project duration will automatically set the below amendment types: "Change of project duration" "Change of reporting periods" "Changes to Annex 1"
| Data sheet - 1. General data | |
AT26 | Change of the reporting periods *Commission Initiated amendment (or) *Consortium Requested amendment
Closed reporting periods can NOT be changed This amendment type can be flagged as Error Amendment by the EU Officer | Automatic | Reporting periods | Change the reporting period and click save.
You can revert back to the previous reporting period details by clicking the Undo button.
To add a new reporting period click Add New Period.
Changing the reporting periods or the project duration, will automatically set the "Change of reporting periods" type:
| Data sheet - 4.2 Periodic reporting and payments |
|
AT27 | Change concerning linked actions *Commission Initiated amendment (or) *Consortium Requested amendment
This amendment type can be activated only by the Commission/Agency. This amendment type can be flagged as Error Amendment by the EU Officer | Automatic | GA Information - Linked Actions | Actor amends the Linked Actions data by using the following options: - Add a Linked Action (click on the 'Add New'link)
- Edit existing or newly added Linked Action
- Remove an existing Linked Action
The removed Linked Actions will not be printed in the document. - Delete newly added Linked Action
- Undo the updates of a specific Linked Action
- Undo ALL Linked Action data updates (including added or removed Linked Actions)
| Data sheet - 1. General data | For projects with Linked Actions enabled in Features configuration (LINKED_ACTIONS.LinkedActions = True) |
AT35 | GA/FPA suspension *Consortium Requested amendment
The new SGA projects cannot be signed if the related FPA is suspended. However, the existing SGA's that do have a linked FPA suspended will be unaffected. If the project is not currently "SUSPENDED", any future suspension (previously submitted via an AT35) can be overridden. Therefore, by overriding a future suspension, the later suspension will be cancelled.
| Manually set by the Beneficiary | Amendment information (the type is set directly in the amendment information tab, no change in another SyGMa tab is required) | Select the tick box for type GA/FPA suspension
Select the pencil icon to enter the suspension date
Enter the suspension date, and suspension justification and click OK You have the option to enter the expected suspension end date, but this is optional.
Click Save
| Data sheet - 5. Consequences of non-compliance, applicable law & dispute settlement forum (if Article 31 is shown in the text) |
|
AT36 | Resuming the action after GA/FPA suspension *Consortium Requested amendment
The suspension end date cannot be earlier than the suspension start date and later than the project end date or the current date, if the project end date has not been defined. | Manually set by the Beneficiary | Amendment information (the type is set directly in the amendment information tab, no change in another SyGMa tab is required) | Select the tick box for type "Resuming the action after GA suspension"
Select the pencil icon to enter the suspension end date
Enter the suspension end date and press "OK"
| |
|
AT37 | GA/FPA termination (early termination) *Consortium Requested amendment
| Automatic | Amendment information | Please click here for more information. |
|
|
AT41** | Change of Annex 2 (estimated budget) *Commission Initiated amendment (or) *Consortium Requested amendment
This amendment type is also available after the end date of the project (but NOT after the final payment) or after the termination date
For a change of Annex 2a, contact the Commission/Agency before preparing your amendment (mandatory) This amendment type can be flagged as Error Amendment by the EU Officer For Lump Sum projects, changes of Work Package budget will automatically select AT41 For projects with budget per Reporting Period, changes of costs breakdown of a reporting period will automatically select AT41
| - Automatically set as a change resulting from another type (see column impact on other amendment types)
- Manually set by the PO in all other cases
| Amendment information | The following amendment types will automatically trigger the setting of the "Change of annex 2" amendment type: - AT1: Addition of new beneficiary
- AT2: Addition of an affiliated entity
- AT3: Addition of an associated partner
- AT5: Beneficiary termination (non-accession to the GA)
- AT11: Change of the coordinator
- AT43a: Change of the maximum grant amount (Annex 2)
- Change of any partner cost break down
If necessary, edit the date for when the changes will start to apply: - Click on the pencil icon
| Annex 2 | |
AT43a
| Change of maximum grant amount (Annex 2) *Commission Initiated amendment (or) *Consortium Requested amendment
This amendment type is not applicable for FPAs. This amendment type can be flagged as Error Amendment by the EU Officer
| Manual | - Project/Beneficiary Financial information
- Amendment information
| The maximum grant amount (Annex 2) is the sum of the requested EU contributions of each individual participant of the project (beneficiary or affiliated entity). The maximum grant amount (Annex 2) cannot be changed directly. If there is a change of requested EU contributions of individual participants and the summary is different, then the maximum grant amount (Annex 2) changes.
When the maximum grant amount (Annex 2) changes, a blocking message will display informing that the "Change of maximum grant amount (Annex 2)" type is not selected and must be selected manually. Usually there is a reshuffle of the budget between participants aiming not to change the maximum grant amount (Annex 2).
When the maximum grant amount (Annex 2) is changed, the "Change of Annex 2" type will automatically be set.
The maximum grant amount (Annex2) cannot be higher than the maximum grant amount (award decision). To correct that, the EU Officer needs to follow the steps described below for AT43b. The maximum grant amount cannot be lower than the amount already paid/consumed in the budgetary system. Image Added
| Data sheet - Section 2 - List of Participants & section 3 - Grant - Maximum grant amount, total estimated eligible costs and contributions and funding rate (Article 5) |
|
AT43b | Change of maximum grant amount (award decision) *Commission Initiated amendment (or) *Consortium Requested amendment
This amendment type can be activated only by the Commission/Agency. This amendment type can be flagged as Error Amendment by the EU Officer | Manual | - Project Financial information
- Amendment information
| This data cannot be edited by the Consortium. Please ask your EU officer to apply the necessary changes to the maximum grant amount (award decision). The maximum grant amount (award decision) can be decreased or increased by the EU Officer.
If the amount is increased, the budgetary commitment should also be increased BEFORE the counter signature of the amendment.
The change of the maximum grant amount (award decision) will activate the Refresh MIM button. The button that can be used to recalculate the MIM amounts according to the change in the maximum grant amount. Changing the maximum grant amount and saving the data will not result in the recalculation of MIM amount(s). Only pressing Refresh MIM will do that (and saving your changes afterwards). The EU Officer can revert back to the previous maximum grant amount (award decision) by clicking the Undo button.
In the Amendment information screen, the EU Officer will manually check the "Change of maximum grant amount (award decision)" type.
| Datasheet - 3. Grant (Article 5.2) |
|
AT44a | Change of the contingency reserve *Commission Initiated amendment (or) *Consortium Requested amendment This amendment type can be flagged as Error Amendment by the EU Officer. | Automatic | - Project Summary
- Financial Information
| The AT44a allows the beneficiaries to adjust their budget, by using the contingency reserve to claim extra costs to cover unforeseen cost claims (e.g. currency fluctuations). In the Financial Information screen, the EU Officer only can edit the Contingency reserve field byclicking on the pencil icon . A pop-up will appear for the EU Officer to insert the amount they wish to claim.
To see the maximum amount by which he/she can increase the maximum grant amount (Annex 2), the EU Officer has to hover over the information icon corresponding to the contingency reserve field. The sum of max grant amount (Annex 2) and the Contingency Reserve not yet activated cannot be higher than the max grant amount (award decision).
Then, the EU Officer clicks on OK and the system displays the modified amount on the screen.
Click Save. This action will trigger the automatic selection of the AT44a clause. The contingency reserve field is then displayed in the Project Summary screen (not editable):
The EU Officer can also cancel the action by clicking on the undo icon .
The Beneficiary has read-only view: - Financial Information screen:
The EU Officer has the option to set the effective date but it is not mandatory. If the effective date is not set, the change will take effect on the entry into force date of the amendment. - To set the effective date, select the pencil icon
- Enter the effective date and click OK.
| Data sheet - 3. Grant (Article 5.2) | If GA Options GAO19 is applicable and selected. |
AT44bAT44b | Activation of the contingency reserve *Commission Initiated amendment (or) *Consortium Requested amendment This amendment type can be flagged as Error Amendment by the EU Officer. | Automatic | Financial Information | The AT44b clause is used to activate the contingency reserve amount and therefore increase the maximum grant amount (Annex 2), as set out in the Data sheet. If AT44b is activated, the following formula applies: Maximum grant amount (Annex 2) + Contingency reserve - Activation of the contingency reserve < Maximum grant award decision. Then, several rules apply: - the Activated Contingency Reserve amount:
- cannot be higher than the contingency reserve
- cannot be a negative number
- cannot be decreased
- in case of an increase of the Activated Contingency Reserve, then, in the same amendment, there should be an increase of the Maximum grant amount (Annex 2) by, at least, an equal amount.
In the Financial Information screen, the EU Officer only can edit the Activated contingency reserve, by clicking on the pencil icon . Then, a pop-up will appear for the EU Officer displaying the: - Activated contingency reserve: the current amount activated, editable (by the EU Officer). This amount can only be increased.
- Changed in this amendment: the amount of the contingency reserve activated in the current amendment.
The Activated Contingency Reserve is never higher than the Contingency Reserve. When the changed amount has been entered, click OK.
The newly modified amount is displayed on the screen.
Then click Save. This action will trigger the automatic selection of the AT44b clause.
The EU Officer can also cancel the action by clicking on the undo icon .
The Beneficiary has read-only view: - Financial Information screen:
The EU Officer has the option to set the effective date but it is not mandatory. If the effective date is not set, the change will take effect on the entry into force date of the amendment. - To set the effective date, select the pencil icon
- Enter the effective date and click OK.
| Data sheet - 3. Grant (Article 5.2) | If GA Options GAO19 is applicable and selected. |
AT50 | Change concerning listed equipment (Only for programmes with depreciation and full purchase cost option) *Commission Initiated amendment (or) *Consortium Requested amendment
This amendment type can be flagged as Error Amendment by the EU Officer | Automatic | - GA Options
- Amendment Information
| Change listed equipment In the GA Options screen, click the pencil icon for GAO39 to edit the listed equipment
Change the List of equipment and click OK
Click save
In the Amendment Information screen, the amendment type "Change concerning listed equipment" will be automatically set.
You have the option to set the effective date but it is not mandatory. If the effective date is not set, the amendment will take effect on the entry into force date. To set the effective date, click the pencil icon
Enter the effective date and click OK.
| Data sheet - 3. Grant - Cost eligibility options (Article 6.2.C.2) | If GA Options GAO39 is applicable and selected |
| Change concerning unit costs/contributions (Annex 2a) *Commission Initiated amendment (or) *Consortium Requested amendment For a change of Annex 2a, contact the Commission/Agency before preparing your amendment (mandatory) This amendment type can be flagged as Error Amendment by the EU Officer | Manual | EU/Beneficiaries - Amendment Information | In the Amendment Information screen select manually the amendment type "AT51 Change concerning unit costs/contributions (Annex 2a)".
Click save
You have the option to set the effective date but it is not mandatory. If the effective date is not set, the amendment will take effect on the entry into force date.
To set the effective date, click the pencil icon
Enter the effective date and click OK
Click save
No document upload is necessary. The Annex 2a will be automatically generated.
| n/a | n/a |
| Change concerning customised unit costs/contributions (Annex 2b) *Commission Initiated amendment (or) *Consortium Requested amendment
For a change of Annex 2b, contact the Commission/Agency before preparing your amendment (mandatory) This amendment type is not applicable for FPAs This amendment type can be flagged as Error Amendment by the EU Officer | Automatic | Beneficiaries - Financial Information | In the Financial Information screen, change the unit cost/contribution as required
Click save
In the Amendment Information screen, the amendment types "AT51a Change concerning customised unit costs/contributions (Annex 2b) and AT41 Change of Annex 2" will be automatically set. You have the option to set the effective date but it is not mandatory. If the effective date is not set, the amendment will take effect on the entry into force date.
To set the effective date, click the pencil icon
Enter the effective date and click OK.
Click save
Click the documents button and upload Annex 2b
| Data sheet - 3. Maximum grant amount, total estimated eligible costs and contributions and funding rate (Article 6.2.D.X Option 5) | Only for programmes with customised unit costs/contributions (HE Research Infrastructure unit cost, AMIF EMN etc) |
AT55
| Change of the prefinancing *Commission Initiated amendment (or) *Consortium Requested amendment
This amendment type can be activated only by the Commission/Agency No payment letter will be generated after an increase of the pre-financing amount. This amendment type can be flagged as Error Amendment by the EU Officer
| Automatic | Financial information | This data cannot be edited by the Consortium. Please ask your EU officer to apply the necessary changes to the prefinancing. The EU Officer can change the amount/percentage of the pre-financing as for them the data is editable.
The entries for paid prefinancing, at the project level, and the entries for processed prefinancing guarantee, at the Beneficiary level, are locked (i.e. not editable or recalculated). The prefinancing amounts can be updated if they are already paid, as long as the associated periodic reporting has not been started yet. Once the periodic reporting has started, no amount updates are allowed anymore and the amendment will be rejected.
Show If |
---|
group | it-administrators, it-view-rights |
---|
| not visible to users: SyGMa 23.4 - story 56617: Once an interim payment has been Once an interim payment has been processed, the system disables the possibility to add any pre-financing entries. If the first pre-financing is paid, but the associated periodic reporting (REPA) has not been launched, then the first pre-financing will be locked, however allowing the possibility to be unlocked. Image Modified After a periodic reporting (REPA) is launched for the first pre-financing, this pre-financing is permanently locked, together with the following one (if applicable). In multi-prefin projects, the number of prefinancing installments can be increased by the EU Officer by pressing the Add prefinancing button.
If MIM applies, one MIM entry will be displayed together with each prefinancing entry. In that case, if a new prefinancing is added, edited or is removed (by clicking ), a Refresh MIM button is generated.
The same button will appear if a change in the maximum grant amount (award decision) is (also) applied.
Press the Refresh MIM button to recalculate the MIM amount(s) in relation to your changes. To recalculate the MIM amount(s) you must press the Refresh MIM button. Only saving your changes will not result in the recalculation of MIM amount(s). You can revert your changes to the latest saved data by clicking the Undo button.
Updating prefinancing will automatically set the "Change of the prefinancing" amendment type:
| Data sheet - 4.2 Periodic reporting and payments (Article 22)
| If pre-financing is applicable (Mono or Multi) |
| Change of the MIM contribution *Commission Initiated amendment (or) *Consortium Requested amendment
This amendment type can be activated only by the Commission/Agency This amendment type is not applicable for FPAs This amendment type can be flagged as Error Amendment by the EU Officer | Automatic | Financial Information | This data cannot be edited: the change in the MIM amounts results from the change in pre-financing and/or the change in maximum grant amount (award decision). The prefinancing amounts can be updated if they are already paid, as long as the associated periodic reporting has not been started yet. Once the periodic reporting has started, no amount updates are allowed anymore and the amendment will be blocked.
You may check the MIM amount(s) by going to the Financial Information screen:
If MIM applies, one MIM entry should be displayed together with each prefinancing entry.
In the Amendment Information screen, the amendment type "AT56 Change of the MIM contribution" will be automatically set.
| Data sheet - 4.2 Periodic reporting and payments (Article 22) | Only for programmes with MIM (for e.g. HORIZON, RFCS) |
AT57a
| Change of the pre-financing guarantee *Commission Initiated amendment (or) *Consortium Requested amendment
This amendment type can be activated only by the Commission/Agency This amendment type can be flagged as Error Amendment by the EU Officer | Automatic | Beneficiaries / Partner - Financial information | This data cannot be edited by the Consortium. Please ask your EU officer to apply the necessary changes to the pre-financing guarantee. The EU officer will change the amount of the pre-financing guarantee (tick the box and introduce the value of the required amount (by default, the box is not flagged).
The EU officer can undo the changes made to the Pre-financing guarantee by clicking the Undo button.
When the pre-financing guarantee is changed, the "Change of the pre-financing guarantee" type will automatically be set.
| Data sheet - 4.2 Periodic reporting and payments (Article 22.3.4)
| If pre-financing guarantee is applicable | AT58
AT57b | Change | of the non-profit rule of joint and several liability of beneficiaries *Commission Initiated amendment (or) *Consortium Requested amendment | This amendment type can be activated only by the Commission/Agency
This amendment type can be flagged as Error Amendment by the EU Officer. | Automatic | - GA Options
- Amendment Information
| This data cannot be edited by the Consortium.
Please ask your EU officer to apply the necessary changes to the non-profit rule The AT57 is reserved for exceptional cases and is open only to the EU. | GA Options
The AT57b is used to add joint and several liability of Beneficiaries, if requested by the EU. This amendment clause can be used only if the GA073 option is applicable for the Grant Agreement (GA). | In the GA Options screen, | the EU officer will select the tick box for GA065 Non profit rule (Data Sheet 4.2) and click saveclick on the pencil icon Image Addedcorresponding to GAO73 to edit Joint and several liability of beneficiaries: Image Added A pop-up window appears to select one of the following options: - 'Limited liability'
'Unconditional' 'Individual'
Image Added Once the new option is selected, click on OK. Then click on Save. If the new option selected is different than the previous one from the GA, the Amendment clause AT57b will be selected in the Amendment information screen. Image Added This amendment type can be unselected, in case of a mistake or if the decision to change the option in force with a different one is taken. | Data Sheet - Section 4.4, Articles 22.2, 22.4 | If GA Options GAO73 is applicable and selected. |
AT58 | Change of the non-profit rule | Image Removed
Image Removed
In the Amendment Information screen, the amendment type "Change of the non-profit rule" will be automatically set.
Image Removed
The EU officer will have the option to set the effective date but it is not mandatory. If the effective date is not set, the amendment will take effect on the entry into force date.
To set the effective date, select the pencil icon Image Removed
Image Removed
Enter the effective date and click OK.
Image Removed
Data sheet - 4.2 Periodic reporting and payments (Article 22.3.4 ) | If GA Options GA065 is applicable and selected | AT59 | Change of the list of CFS exempted participants (CFS waive)*Commission Initiated amendment (or) *Consortium Requested amendment
This amendment type can be activated only by the Commission/Agency This amendment type can be flagged as Error Amendment by the EU Officer | Automatic | Beneficiaries - Financial | - GA Options
- Amendment Information
| This data cannot be edited by the Consortium. Please ask your EU officer to apply the necessary changes to the | CFS flag.non-profit rule. In the GA Options screen, the EU officer will select the tick box for GA065 Non profit rule (Data Sheet 4.2) and click save Image Added Image Added In the Amendment Information screen, the amendment type "Change of the non-profit rule" will be automatically set. Image Added The EU officer will have the option to set the effective date but it is not mandatory. If the effective date is not set, the amendment will take effect on the entry into force date. To set the effective date, select the pencil icon Image Added Image Added Enter the effective date and click OK. Image Added
| Data sheet - 4.2 Periodic reporting and payments (Article 22.3.4 ) | If GA Options GA065 is applicable and selected |
AT59 | Change of the list of CFS exempted participants (CFS waive) | The CFS flag can be changed for a Beneficiary or an Affiliated Entity by the EU Officer.
Image Removed
When the CFS waive flag is changed, the "Change of the list of CFS exempted participants (CFS Wave)" type will automatically be set.
Image Removed
Data sheet - 4.3 Certificates (Article 24) | If CFS is applicable | AT60** | Change due to errors/mistakes This amendment type can be activated only by the Commission/Agency
*Commission Initiated amendment (or) *Consortium Requested amendment
This amendment type | is also available after the end date of the project (but NOT after the final payment) or after the termination datecan be activated only by the Commission/Agency | This amendment type can be flagged as Error Amendment by the EU Officer | Automatic | Beneficiaries - Financial Information | This data cannot be edited by the Consortium. Please ask your EU officer to apply the necessary changes to the CFS flag. The CFS flag can be changed for a Beneficiary or an Affiliated Entity by the EU Officer. Image Added When the CFS waive flag is changed, the "Change of the list of CFS exempted participants (CFS Wave)" type will automatically be set. Image Added
| Data sheet - 4.3 Certificates (Article 24) | If CFS is applicable |
AT60** | Change due to errors/mistakes | On demand by EU (the PO needs to request the Service Desk to enable the clause) | This amendment type is used in the exceptional cases when errors/mistakes need to be corrected and the option to select the applicable clause as an error amendment is not available: Image Removed | AT60gcCorrect Annex 5 *Commission Initiated amendment (or) *Consortium Requested amendment
This This amendment type is also available after the end date of the project (but NOT after the final payment) or after the termination date This amendment type can be activated only by the Commission/Agency This This amendment type can be flagged as Error Amendment by the EU Officer
| On demand by EU (the PO needs to request the Service Desk to enable the clause) Manual |
| This amendment type is used to correct the Annex 5Image Removed You have in the exceptional cases when errors/mistakes need to be corrected and the option to set the effective date but it is not mandatory. If the effective date is not set, the amendment will take effect on the entry into force date.To set the effective date, click the pencil icon Image Removed Image Removed Choose the effective date and click OK Image Removed select the applicable clause as an error amendment is not available: Image Added |
|
|
| Correct Annex 5 * | AT72a | Change of blended finance investment component
(Only for programmes with blended finance single action)
*Commission Initiated amendment (or) *Consortium Requested amendment
| This This amendment type can be activated only by the Commission/Agency This amendment type can be flagged as Error Amendment by the EU Officer | Automatic | - GA Options
- Amendment Information
| In the GA Options screen, click the pencil iconImage Removed for GA090 to edit the blended finance investment component Manual |
| This amendment type is used to correct the Annex 5 Image Added You have the option to set the effective date but it is not mandatory. If the effective date is not set, the amendment will | Image Removed
Change the investment component amount and click OK
Image Removed
Click save
Image Removed
In the Amendment Information screen, the amendment type "AT72a Change of blended finance investment component" will be automatically set.
Image Removed
You have the option to set the effective date but it is not mandatory. If the effective date is not set, the amendment will take effect on the entry into force date. To set the effective date, | select | Image Removed Image Added | Image RemovedImage Added | Enter Choose the effective date and click OK | . | Image Removed
Data sheet - 1. General data (Article 1, 3, Annex 6) | If GA Options GA090 is applicable | Image Added
|
|
|
AT72a | Change of blended finance investment component | AT72b | Change of Annex 6 (Only for programmes with annex 6blended finance single action) *Commission Initiated amendment (or) *Consortium Requested amendment
This amendment type can be flagged as Error Amendment by the EU Officer | AutomaticManual | - GA Options
- Amendment Information
| In the Amendment Information GA Options screen, select the tick box for AT72b Change of Annex 6 and click saveclick the pencil iconImage Added for GA090 to edit the blended finance investment component Image Added Change the investment component amount and click OK Image Added Click save Image Added In the Amendment Information screen, the amendment type "AT72a Change of blended finance investment component" will be automatically set. Image AddedImage Removed You have the option to set the effective date but it is not mandatory. If the effective date is not set, the amendment will take effect on the entry into force date. To set the effective date, select the pencil icon Image Modified Image RemovedImage Added Enter the effective date and click OK. Image Removed Click Save Image Removed Click the documents button and upload Annex 6 Image Removed Image Removed Image Added
| Data sheet - 1. General data (Article 1, 3, Annex 6) | If GA Options GA090 is applicable |
AT72b | Change of Annex 6 (Only Only for programmes with blended finance (single action) Used by HE EIC Accelerator Blended Finance | AT101
Transfer of the Grant Agreement to another granting authorityannex 6) *Commission Initiated amendment | This amendment type can be activated only on demand of the Commission/Agency.
(or) *Consortium Requested amendment
| This amendment type can be flagged as Error Amendment by the EU Officer | Manual | Amendment Information | In the Amendment Information screen, select the tick box for AT72b Change of Annex 6 and click save Image Added You have the option to set the effective date but it is not mandatory. If the effective date is not set, the amendment will take effect on the entry into force date. To set the effective date, select the pencil icon Image Added Image Added Enter the effective date and click OK Image Added Click Save Image Added Click the documents button and upload Annex 6 Image Added Image Added
| Data sheet - 1. General data (Article 1, 3, Annex 6) | Only for programmes with blended finance (single action) Used by HE EIC Accelerator Blended Finance |
| Transfer of the Grant Agreement to another granting authority *Commission Initiated amendment
This amendment type can be activated only on demand of the Commission/Agency. This amendment type can be flagged as Error Amendment by the EU Officer | On demand by EU (the PO needs to request the Service Desk to enable to clause) | GA Information | By selecting this amendment clause the following fields will become editable in the GA Information screen | On demand by EU (the PO needs to request the Service Desk to enable to clause) | GA Information | By selecting this amendment clause the following fields will become editable in the GA Information screen:
- All changes are done by selecting another Granting Authority Service via the 'Change' link (no "undo" button available on the screen).
The hyperlink next to Granting Authority Service: 'Change' is displayed and can be edited ONLY if AT 101 is selected. - Granting Authority Service
- Granting Authority Service location
You have the option to set the transfer date but it is not mandatory. If the transfer date is not set, the amendment will take effect on the entry into force date. - To set the transfer date, click the pencil icon
Image Removed Enter the transfer date and click OK. Show If |
---|
group | it-administrators, it-view-rights |
---|
| not visible to users - story SYGMA-56638 - replace text above with this one: - To set the transfer date, the new CL2 key and the Budgetary system, click the pencil icon
|
---|
|
Image Removed
This amendment clause has to be signed by: the Authorising Officer requesting the transfer the Authorising Officer to whom the GA is transferredthe ConsortiumImage Added Image Added
|