PROJECT DESCRIPTION
BACKGROUND
Concrete is the main building material used in civil engineering construction. Due to the immense energy consumption and the large amounts of cement used, the production of cement contributes 5% of the man-made annual CO2 emission worldwide.
OBJECTIVES
The INSU-SHELL project aimed to minimise the amount of concrete necessary in the construction of the facades by using a high-tech, thermally insulated textile reinforced concrete (TRC) technology. The new system would enable the construction of thinner walled building facades offering a superior performance than comparable materials made out of GRC (glass fibre reinforced concrete). Similarly, conventional steel reinforced concrete facades require a minimum thickness of 70 mm, whereas the new reinforced concrete would allow wall facades of just 10-20 mm. The project would demonstrate the economic and environmental friendly benefits of the TRC technology in a full-scale industrial application i.e. used in the construction of the facade of a large public building. Improved insulation offered by the technology would enable energy savings. Furthermore, a reduction of CO2 emissions would be achieved both in the production process (through reduced need for concrete) as well as during implementation and recycling.
RESULTS
The demonstration of the new technology was successful, although the area demonstrated, was smaller than originally envisaged. The technology was implemented as part of the new building facade of the (INNOTEX) textile research centre at RWTH Aachen University. The system was developed according to the architectural and structural-physical requirements of the new building. The design met these requirements and shows the potential of the new TRC technology. According to the beneficiary, it is superior to conventional materials in terms of load bearing capacity, overall wall thickness and efficiency.
Most of the expected goals were achieved:
The construction of the building started, however, around one year earlier than originally planned. This placed the project under pressure to produce the facade elements in time. In turn, this meant higher staff and external assistance costs and resulted in higher specific costs – estimated at around €450 /m². In order to be competitive, the beneficiary says these costs would need to fall below €300 /m². It is convinced that this threshold will be met in the planned second university building.
In terms of job creation the potential is very high, once the economic breakthrough is achieved. This is one of the few high tech products, where manual work input is higher than for the conventional alternative. Thus there would be a real net job creation.
Further information on the project can be found in the project's layman report (see "Read more" section).