Step 5: The EU reviews the submitted Termination Report.  

Upon submission the EU will assess the Termination Report.

In case the EU judges that the Termination Report is incomplete, the EU can request for a revision of the report. In this case, the coordinator and terminated beneficiary will be notified, and the cycle repeats as of Step 1 and the EU will re-assess, upon re-submission of the revised Termination Report.

In case the EU judges that the Termination Report is complete, the EU will assess any costs submitted by the terminated beneficiary. On the basis of the submitted costs and the distribution of payments to the terminated beneficiary, the EU will calculate the 'amount which is due' for the terminated beneficiary.  

Further the EU will complete the process for the Termination Report. As a result, the terminated beneficiary and the coordinator will be notified, via Formal Notifications, about the 'amount which is due', and: 

  • If the Commission/Agency owes amounts to the beneficiary, those amounts will be included in the calculation of the next payment to the consortium (interim or final) 
  • if the beneficiary has received excess, those amounts must be repaid by it, usually to the consortium via the coordinator. 

The terminated beneficiary's financial statement will be automatically included in the periodic report for the next reporting period. 

...

usercmarcos
groupiknowplus-administrators, iknowplus-view rights

not visible to the users: Replace the section 5 with the sections one below when PPXMS 8.0 goes into PROD: Add Heading 2 to each section title

Step 5: The EU reviews the submitted Termination Report   

...

, the EU will assess the Termination Report. In case the EU judges that the Termination Report is incomplete, the EU can request for a revision of the report. In this case, the coordinator and terminated beneficiary will be notified via Formal Notifications, and the cycle repeats as of Step 1 and the EU will re-assess, upon re-submission of the revised Termination Report. In case the EU judges that the Termination Report is complete, the EU will assess any costs submitted by the terminated beneficiary. On the basis of the submitted costs and the distribution of payments to the terminated beneficiary, the EU will calculate the 'amount which is due' for the terminated beneficiary.  

Further the EU will complete the process for the Termination Report. As a result, the terminated beneficiary and the coordinator will be notified in a Beneficiary Termination Calculation Pre-information Letter, via Formal Notifications, about the 'amount which is due' and the balance, and: 

  • If the balance is in favour of the terminated beneficiary, those amounts will be included in the calculation of the next payment to the consortium (interim or final) 
  • if the balance is in favour of the consortium (i.e. the beneficiary has received excess), it must repay the amount, usually to the consortium via the coordinator. 

Step 6a: The Coordinator does not agree with the content of the Beneficiary Termination Calculation Letter and uploads observations 

A letter containing the decision regarding the 'amount which is due' is sent by the EU via a Formal Notification. The Coordinator and the terminated beneficiary will be notified about the sending of this letter via the Participant Notification System. The Formal Notification will be found under "My Notifications" section of the Funding & Tenders Portal and needs acknowledgment of receipt.

Image Modified

To acknowledge the Formal Notification, click on the link and, when prompted, provide your EU Login password and click Sign.

Image Modified

You will now be able to download all letter attachment individually (by clicking on the corresponding arrow) or an archive (by clicking Download .zip).

Image Modified 

After receiving this letter and its attachments, the Coordinator has 30 days to submit observations on the letter if it does not agree with its content (including any observations by the terminated beneficiary). 

If you need to consult the letter, you can find it in the task that has been just created for the upload of observations - click the link to the document to download it.

Image Modified

The letter is also stored under Process Documents - it can be accessed and downloaded from there. To download it, click the link and then the download icon:

Image Modified

Image Modified

To upload the observations document, click on

...

the Upload button:

Image Modified

...

Then click Add new

...

attachment to attach the document:

Image Modified

To remove the attached document, you just need to click on the "X". 

Image Modified

Once the uploading is finished,

...

click OK:

Image Modified

After uploading the observations,

...

click Submit to EU to

...

send them to the EU. A notification will be sent to the Commission to inform that the observations have been submitted.

Image Modified

If the Observations document has been successfully submitted, the corresponding action is not available anymore. The submitted Observations document will be added to

...

the Process documents section.

Image Modified


Step 6b: The Coordinator agrees with the content of the Beneficiary Termination Calculation Letter and closes the process without observations

If the Coordinator and the terminated beneficiary agree with the content of the letter, complete the process without sending any observations. For this, you need to click the Close without Observations button:

Image Modified

After the observations have been submitted or the process has been closed without observations, the EU will state its final position via a Formal Notification containing the "Beneficiary Termination Calculation Final Letter". 

The Coordinator will be notified about the sending of this letter via the Participant Notification System. The Formal Notification will be found under "My Notifications" section of the Funding & Tenders Portal and needs acknowledgment of receipt.

Image Modified

As before, to acknowledge the Formal Notification, click on the link and, when prompted, provide your EU Login password and click Sign. You will be then able to download all letter attachment individually (by clicking on the corresponding arrow) or an archive (by clicking Download .zip).

Image Modified

The process will be now completed and can be found in the Archived Processes section.

Image Modified


Step 7: The Coordinator confirms the reimbursement from the terminated beneficiary 

In case of the beneficiary has received amounts in excess, the coordinator will have to confirm that it has been reimbursed by the terminated beneficiary

To upload the confirmation document, click on

...

the Upload button:

Image Modified

...

Then click Add new

...

attachment to attach the document:

Image Modified

To remove the attached document, you just need to click on the "X"

Image Modified

Once the uploading is finished,

...

click OK:

Image Modified

After uploading the confirmation,

...

click Complete to send it to the EU. 

Image Modified

Image Modified

If the confirmation document has been successfully submitted, the corresponding action is not available anymore.

Image Modified